Coastal Villas Paraparaumu

Holmes Construction was engaged by Metlifecare on the Coastal Villas reclad project located in Paraparaumu. This project is the recladding of all units in the retirement complex. Holmes have been involved as Main Contractor since commencement in 2018.

Each duplex is encapsulated within a scaffold tent to mitigate weather issues. The buildings are re-roofed, have new eaves formed, windows are replaced and a new weather board cladding system is provided over a cavity system. New wall insulation is provided and linings to exterior walls are fitted and finished. A number of units are also fully redecorated at the same time.

Work to date has been completed successfully to a rolling programme, and has required close liaison with the client to minimise disruption to residents. Holmes have completed 37 duplexes, with an additional three underway.

Previous
Previous

Wellington Regional Aquatic Centre (WRAC)

Next
Next

Kate Sheppard Apartments